Solar Power (In Progress Updating)

Site Name : Local Basic
Total Capacity : 1342.545kWp
Report Date : 20/11-3/12/2023 (Monday-Sunday)
Phase : 1
Capacity: 871.905kWp
Area: Lobby, Auto CNC A, Auto CNC B, Auto CNC C

Mounting Structure 
Lobby - 100% Completed
Auto CNC A - 100% Completed
Auto CNC B - 100% Completed
Auto CNC C - 60% Completed

PV Module Lifted on Roof
Total Panel = 1571 pcs
Lobby - 100% Completed
Auto CNC A - 100% Completed
Auto CNC B - 100% Completed
Auto CNC C - 50% Completed

PV Module Installation
Lobby - 100% Completed
Auto CNC A - 100% Completed
Auto CNC B - 100% Completed
Auto CNC C - 50% Completed

DC Trunking - 87% Completed
Inverter Installation - 100% Completed
PVMSB Installation - 0% Completed
AC Trunking - 50% Completed
AC Cable Installation - 0% Completed
Interconnection Works - 0% Completed

———————————————
Phase : 2
Capacity: 470.640kWp
Area: Manual CNC, Casting, Production, Curve Roof

Mounting Structure 
Man. CNC - 100% Completed
Casting - 70% Completed
Production - 0% Completed
Curve Roof - 0% Completed

PV Module Lifted on Roof
Total Panel = 848 pcs
Man. CNC - 100% Completed
Casting - 20% Completed
Production - 0% Completed
Curve Roof - 0% Completed

PV Module Installation
Man. CNC - 100% Completed
Casting - 20% Completed
Production - 0% Completed
Curve Roof - 0% Completed

DC Trunking - 50% Completed
Inverter Installation - 100% Completed
PVMSB Installation - 0% Completed
AC Trunking - 0% Completed
AC Cable Installation - 0% Completed
Interconnection Works - 0% Completed